Home | Inquiry | Contact Us | Site map | Login
Projects Categories
Solar Power Plant
Cement Plant
Steel Plant
Power Plant
Sewage Treatment Plant
Packaging Plant
Institutional Work
Gas Compressor Stations
Industrial Projects
Infrastructure Work
Food Industry
Residential & Commercial Work
Earth Work
Inquiry Form
 
 
 
 
 
 
 
CAPTCHA Image
 
 
 
Latest Projects
Executed Projects / Ongoing Projects
Konark Solar Power Plant, Kutch
 
Client Name : Vikram Proener Projects
Location : Khodasar - Lakadia Village, Kutch.
Project Type : Solar Power Plant
Project Start Date : 10th Oct 2011
Mobilization Duration : 10th to 20th Oct 2011
Project Finish Date : 15th Dec 2011
Demobilization Duration : 15th Dec to 25th Dec 2011
Scope : Solar PV Module Slab Foundations, Transformer Foundations, Main Gate.
Features :
1. Concrete : 2374.99 Cubic Meter
2. Shuttering Work : 8380.29 Square Meter
3. Reinforcement : 101.706 MT
4. Completion Time: 45 Days
Interesting Facts :
• 15,528 Nos. of Cement Bags were used...
• 1,01,706 Kgs of 8mm dia Reinforcement Steel were used...
• 20,646.84 Meter Long Reinforcement Cages was prepared...
• 1,018 kgs of Binding Wire was used to prepare Reinforcement Cages
• 20,646.84 Meter Long concrete Slabs were casted...
• 41,293.68 Meter Long 200mm shuttering work was carried out...
• 517 Nos of Expansion Joints were provided in Concrete Slabs...
• 7,337.33 Liters of Fuel were consumed throughout the Project...
• 11, 97,000 Liters of water were consumed throughout the Project...
• 1, 07, 05,764 Meters (Approx Value) on ground transportation of concrete were done...
• 35,560 Attended Labour Working Hours has been in register in this project...
• Zero Injury was recorded throughout the project execution...
Visual Percept Solar Power Plant, Surel
 
Client Name : Sterling and Wilson Ltd
Location : Surel Village, Surendranagar.
Project Type : Solar Power Plant
Project Start Date : 17th Oct 2011
Mobilization Duration : 17th to 30th Oct 2011
Project Finish Date : 4th Dec 2011
Demobilization Duration : 4th Dec to 8th Dec 2011
Scope : Solar PV Module Pile Foundations.
Features :
1. Concrete Pile: 1,110 Nos.
2. Pile Cap Shuttering : 627 Square Meter
3. Reinforcement : 16,650 kgs
4. Foundation Bolts : 4,440 Nos
5. Completion Time: 34 Days
Interesting Facts :
• 2,830 Nos. of Cement Bags were used...
• 16,650 Kgs of 8mm dia Reinforcement Steel were used...
• 17,680 Working hours has been attended in register throughout the project...
• 4,440 Nos of foundation bolts were accurately installed in pile caps…
• Zero Injury was recorded throughout the project execution...
TATA Power Solar Power Plant, Mithapur
 
Client Name : TATA BP Solar Ltd
Location : Mithapur Village, Jamnagar.
Project Type : Solar Power Plant
Project Start Date : 12th July 2011
Mobilization Duration : 12th to 25th July 2011
Project Finish Date : 30th Jan 2012
Demobilization Duration : 29th Dec to 30th Jan 2012
Scope : Control Room Building, CSS Foundation, Chain link Fence, Road and Drain Network Etc.
Features :
1. Excavation : 21,554 Cubic Meter
2. Concrete : 2385 Cubic Meter
3. Shuttering Work : 10,732 Square Meter (Approx)
4. Reinforcement Steel : 69 MT
5. Structural Steel : 106 MT
6. Completion Time: 6 Months
Interesting Facts :
• 20,533 Nos. of Cement Bags were used...
• 69,000 Kgs of Reinforcement Steel were used...
• 700 kgs of Binding Wire was used to prepare Reinforcement Cages
• 8382.5 Liters of Fuel were consumed throughout the Project...
• 15,33,000 Nos of Brick/Blocks were used…
• 3,209 Square meter Plaster work executed…
• 1,200 Square meter False Work (Ceiling and Flooring) executed…
• 1,150 Square meter RCC Flooring work executed…
• 96 MT Hot Dipped Galvanized Structural Steel were used…
• 5,500 Square meter Chain Link Fence were used to cover the boundary…
• 29,600 Square meter 150mm thick Granular Sub Base prepared for internal road network
• 29,600 Square meter 150mm thick Black Trap Metal work done for internal road network
• 5,836 Square meter 50mm thick Bituminous Carpet work done for approach road and internal road network
• Zero Injury was recorded throughout the project execution...
 
Fly Ash Handling Project, Vanakbori
 
Client Name : Mecgale Pneumatics Pvt. Ltd.
Location : Vanakbori Thermal Power Station, Kheda.
Project Type : Heavy Industrial Project
Project Start Date : 30th Jun 2010
Mobilization Duration : 30th Jun to 20th July 2010
Project Finish Date : 25th Dec 2011
Demobilization Duration : 25th Dec 2011 to 15th Jan 2012
Scope : Fly Ash Silo, Compressor Building, MCC Room, Intermediate Silo Structures, Heavy Foundation Work.
Features :
1. Excavation : 6,542 Cubic Meter
2. Concrete : 2,752 Cubic Meter
3. Shuttering Work : 5,700 Square Meter (Approx)
4. Reinforcement Steel : 238 MT
5. Structural Steel : 2,505 kg
6. Foundation Bolts : 765 Nos
7. Completion Time: 16 Months
Interesting Facts :
• 27,410 Nos. of Cement Bags were used...
• 2,38,000 Kgs of Reinforcement Steel were used...
• 2,380 kgs of Binding Wire was used to prepare Reinforcement Cages
• 35.5 meter above GL and 4.0 meter below GL RCC Silo was constructed…
• 12,500 mm inner diameter of RCC Silo…
• 13,300 mm outer diameter of RCC Silo…
• 2,018 Square meter slip form shuttering was sued to construction the silo…
• 2000 MT capacity of RCC main silo and 200 MT capacity of Intermediate silo…
• 2,300 Square meter slab on grade was constructed as internal RCC road…
• 1,000 meter pipe rack and its foundation were constructed…
• 3 Nos of Weigh Bridge were constructed…
• 12.0 meter high intermediate silo foundation was constructed …
• Zero Injury was recorded throughout the project execution...
 
 
 
  Home  |  About Us  |  Projects |  Services |  Contact Us  |  B-Con Profile  |  Inquiry  |  Photo Gallery  |  Sitemap  |  Login Designed By : Shah Net
  Bhagyashree Construction © 2011 All Rights Reserved