Konark Solar Power Plant, Kutch |
|
|
Client Name : |
Vikram Proener Projects |
Location : |
Khodasar - Lakadia Village, Kutch. |
Project Type : |
Solar Power Plant |
Project Start Date : |
10th Oct 2011 |
Mobilization Duration : |
10th to 20th Oct 2011 |
Project Finish Date : |
15th Dec 2011 |
Demobilization Duration : |
15th Dec to 25th Dec 2011 |
Scope : |
Solar PV Module Slab Foundations, Transformer Foundations, Main Gate. |
Features : |
1. Concrete : 2374.99 Cubic Meter
2. Shuttering Work : 8380.29 Square Meter
3. Reinforcement : 101.706 MT
4. Completion Time: 45 Days
|
Interesting Facts : |
• 15,528 Nos. of Cement Bags were used...
• 1,01,706 Kgs of 8mm dia Reinforcement Steel were used...
• 20,646.84 Meter Long Reinforcement Cages was prepared...
• 1,018 kgs of Binding Wire was used to prepare Reinforcement Cages
• 20,646.84 Meter Long concrete Slabs were casted...
• 41,293.68 Meter Long 200mm shuttering work was carried out...
• 517 Nos of Expansion Joints were provided in Concrete Slabs...
• 7,337.33 Liters of Fuel were consumed throughout the Project...
• 11, 97,000 Liters of water were consumed throughout the Project...
• 1, 07, 05,764 Meters (Approx Value) on ground transportation of concrete were done...
• 35,560 Attended Labour Working Hours has been in register in this project...
• Zero Injury was recorded throughout the project execution...
|
|
|
|
|
|
|
Visual Percept Solar Power Plant, Surel |
|
|
Client Name : |
Sterling and Wilson Ltd |
Location : |
Surel Village, Surendranagar. |
Project Type : |
Solar Power Plant |
Project Start Date : |
17th Oct 2011 |
Mobilization Duration : |
17th to 30th Oct 2011 |
Project Finish Date : |
4th Dec 2011 |
Demobilization Duration : |
4th Dec to 8th Dec 2011 |
Scope : |
Solar PV Module Pile Foundations. |
Features : |
1. Concrete Pile: 1,110 Nos.
2. Pile Cap Shuttering : 627 Square Meter
3. Reinforcement : 16,650 kgs
4. Foundation Bolts : 4,440 Nos
5. Completion Time: 34 Days
|
Interesting Facts : |
• 2,830 Nos. of Cement Bags were used...
• 16,650 Kgs of 8mm dia Reinforcement Steel were used...
• 17,680 Working hours has been attended in register throughout the project...
• 4,440 Nos of foundation bolts were accurately installed in pile caps…
• Zero Injury was recorded throughout the project execution...
|
|
|
|
|
|
|
TATA Power Solar Power Plant, Mithapur |
|
|
Client Name : |
TATA BP Solar Ltd |
Location : |
Mithapur Village, Jamnagar. |
Project Type : |
Solar Power Plant |
Project Start Date : |
12th July 2011 |
Mobilization Duration : |
12th to 25th July 2011 |
Project Finish Date : |
30th Jan 2012 |
Demobilization Duration : |
29th Dec to 30th Jan 2012 |
Scope : |
Control Room Building, CSS Foundation, Chain link Fence, Road and Drain Network Etc. |
Features : |
1. Excavation : 21,554 Cubic Meter
2. Concrete : 2385 Cubic Meter
3. Shuttering Work : 10,732 Square Meter (Approx)
4. Reinforcement Steel : 69 MT
5. Structural Steel : 106 MT
6. Completion Time: 6 Months |
Interesting Facts : |
• 20,533 Nos. of Cement Bags were used...
• 69,000 Kgs of Reinforcement Steel were used...
• 700 kgs of Binding Wire was used to prepare Reinforcement Cages
• 8382.5 Liters of Fuel were consumed throughout the Project...
• 15,33,000 Nos of Brick/Blocks were used…
• 3,209 Square meter Plaster work executed…
• 1,200 Square meter False Work (Ceiling and Flooring) executed…
• 1,150 Square meter RCC Flooring work executed…
• 96 MT Hot Dipped Galvanized Structural Steel were used…
• 5,500 Square meter Chain Link Fence were used to cover the boundary…
• 29,600 Square meter 150mm thick Granular Sub Base prepared for internal road network
• 29,600 Square meter 150mm thick Black Trap Metal work done for internal road network
• 5,836 Square meter 50mm thick Bituminous Carpet work done for approach road and internal road network
• Zero Injury was recorded throughout the project execution...
|
|
|
|
|
|
Fly Ash Handling Project, Vanakbori |
|
|
Client Name : |
Mecgale Pneumatics Pvt. Ltd. |
Location : |
Vanakbori Thermal Power Station, Kheda. |
Project Type : |
Heavy Industrial Project |
Project Start Date : |
30th Jun 2010 |
Mobilization Duration : |
30th Jun to 20th July 2010 |
Project Finish Date : |
25th Dec 2011 |
Demobilization Duration : |
25th Dec 2011 to 15th Jan 2012 |
Scope : |
Fly Ash Silo, Compressor Building, MCC Room, Intermediate Silo Structures, Heavy Foundation Work. |
Features : |
1. Excavation : 6,542 Cubic Meter
2. Concrete : 2,752 Cubic Meter
3. Shuttering Work : 5,700 Square Meter (Approx)
4. Reinforcement Steel : 238 MT
5. Structural Steel : 2,505 kg
6. Foundation Bolts : 765 Nos
7. Completion Time: 16 Months
|
Interesting Facts : |
• 27,410 Nos. of Cement Bags were used...
• 2,38,000 Kgs of Reinforcement Steel were used...
• 2,380 kgs of Binding Wire was used to prepare Reinforcement Cages
• 35.5 meter above GL and 4.0 meter below GL RCC Silo was constructed…
• 12,500 mm inner diameter of RCC Silo…
• 13,300 mm outer diameter of RCC Silo…
• 2,018 Square meter slip form shuttering was sued to construction the silo…
• 2000 MT capacity of RCC main silo and 200 MT capacity of Intermediate silo…
• 2,300 Square meter slab on grade was constructed as internal RCC road…
• 1,000 meter pipe rack and its foundation were constructed…
• 3 Nos of Weigh Bridge were constructed…
• 12.0 meter high intermediate silo foundation was constructed …
• Zero Injury was recorded throughout the project execution...
|
|
|
|
|
|
|
|
|
|
|
|